AQW 49186/22-27 Written question to the Minister for Infrastructure
To ask the Minister for Infrastructure, pursuant to AQW 45995/22-27, to detail the (i) scope; (ii) start date; (iii) expected completion date; and (iv) publication arrangements, for the ongoing route study of the A26 Lisnevenagh Road.
Asked by Sian Mulholland MLA on 19 June 2026
- Answered
- Written
- Tabled
- 19 June 2026
- Answer due by
- 6 July 2026
- Answered
- 29 June 202610 days after tabling
- Department
- Department for Infrastructure
- Priority question
- No
Answer
The A26 Route Study is a review of the signage, lining, bollards, cats eyes and other infrastructure along the A26 to ensure that this infrastructure is in accordance with the latest standards. It is an ongoing review and not subject to publication, however the information gathered will be used to inform the planning and prioritisation of repairs and replacement works along the route.